Three EVs on a 200 amp service with load sharing
A three-EV household estimates a 140 A non-EV design load. It is considering three 48 A ports and a controller set to a 60 A site limit.
Compare the configured limit to the screened site budget. A lower configured ceiling reduces the demand assigned to EV charging.
Results
- Overnight energy per EV
- 31.1 kWh
- Power per active EV
- 3.84 kW
- Active ports at once
- 3 / 3
- Power per EV when all run
- 3.84 kW
- Overnight range per EV
- 96.4 mi
- Screened continuous EV budget
- 48 A
- Applied total charging current
- 48 A
- Headroom at configured limit
- -15 A
- Headroom with applied load
- 0 A
- Headroom if all ports use maximum
- -120 A
The configured EV limit exceeds the screened headroom. Results apply the lower service budget.
Worksheet inputs
- Service or panel rating
- 200 A
- Existing non-EV design load
- 140 A
- Connected EVs or EVSE ports
- 3
- Maximum charging current per port
- 48 A
- Configured site charging limit
- 60 A
- Single-phase line-to-line voltage
- 240 V
- Overnight dwell time
- 9 h
- Wall-to-battery efficiency
- 90 %
- Fleet driving efficiency
- 3.1 mi/kWh
Calculation notes
Subtract the existing non-EV design load from the service rating and divide by 1.25 to screen the new continuous EV charging budget. The applied site limit is also capped by the controller setting and connected port ratings.
If each port can receive at least the assumed 6 A minimum, all vehicles share the current at once. Otherwise, the calculator estimates rotating groups of active ports with equal dwell time over the night.
This is a conservative single-phase planning check. Use a qualified designer for the adopted load calculation, listed energy-management equipment, branch circuits, and phase balancing.
Frequently asked questions
Why is a 60 A controller setting high for the three-EV example?
Sixty amps of charging adds 75 A of screened demand. That exceeds the 60 A of design headroom available.
Would three separate 48 A chargers pass this simple unmanaged check?
Their 144 A of charging current screens at 180 A. The worksheet shows 120 A more than the current headroom.