Three EVs on a 200 amp service with load sharing

A three-EV household estimates a 140 A non-EV design load. It is considering three 48 A ports and a controller set to a 60 A site limit.

Compare the configured limit to the screened site budget. A lower configured ceiling reduces the demand assigned to EV charging.

Inputs

Unit system

Results

Overnight energy per EV
31.1 kWh
Power per active EV
3.84 kW
Active ports at once
3 / 3
Electrical load and remaining headroom
Managed EV service load3 of 3 EVs can charge at the same time at the screened site limit.Modeled panel demand (A)Service 200 AExisting 140 AEV load × 1.25 60 AConnected EVs1233 active at once16 A per active port
Power per EV when all run
3.84 kW
Overnight range per EV
96.4 mi
Screened continuous EV budget
48 A
Applied total charging current
48 A
Headroom at configured limit
-15 A
Headroom with applied load
0 A
Headroom if all ports use maximum
-120 A

The configured EV limit exceeds the screened headroom. Results apply the lower service budget.

Calculation notes

Subtract the existing non-EV design load from the service rating and divide by 1.25 to screen the new continuous EV charging budget. The applied site limit is also capped by the controller setting and connected port ratings.

If each port can receive at least the assumed 6 A minimum, all vehicles share the current at once. Otherwise, the calculator estimates rotating groups of active ports with equal dwell time over the night.

This is a conservative single-phase planning check. Use a qualified designer for the adopted load calculation, listed energy-management equipment, branch circuits, and phase balancing.

Frequently asked questions

Why is a 60 A controller setting high for the three-EV example?

Sixty amps of charging adds 75 A of screened demand. That exceeds the 60 A of design headroom available.

Would three separate 48 A chargers pass this simple unmanaged check?

Their 144 A of charging current screens at 180 A. The worksheet shows 120 A more than the current headroom.